Billing guide
How to understand net metering and your solar bill
Net metering does not automatically erase a bill or turn a solar proposal into a guaranteed credit. Use it to organize what the system generates, what the service consumes and which billing treatment must be verified from current documents.

Net metering versus interconnection
Interconnection is the process through which distributed generation can relate to the grid under applicable requirements. Net metering concerns how generation, consumption and excess are recorded and treated after the relevant agreement and configuration exist. Captured Act 114-2007 contemplates interconnection and bill credits for renewable generation, but it does not replace an individual account's agreement, tariff or technical review.
LUMA's page separates application, document review, technical validation, agreements and bidirectional-meter steps. If one remains pending, a credit discussion does not establish that the system is ready to operate. Use the interconnection guide to organize that record. If you are organizing a solar decision from the start, the project starting guide helps separate price, installation and billing.
- Interconnection: application, documents, validation and technical conditions.
- Billing: period, tariff, meter information and consumption or credit entries.
- Production: energy the system records; it is not by itself a savings or final-balance result.
Source: Puerto Rico Net Metering Program Act, Act No. 114 of August 16, 2007, as amended, Pasos de Medición Neta
Information to review on a bill
Read a bill as a record for a defined period, not a universal scorecard for the system. Collect bills from before and after any tariff change, and note service period, readings or consumption, charges shown, any credit line, and the balance. Keep the full bill because a cropped image can omit notes or adjustments.
The captured Energy Bureau order says a revised tariff book included updates to the Net Metering Credit and related provisions. No dollar figures are reproduced here: verify the currently published version and ask LUMA to explain any line item the document does not make clear. For production records, see what to review in system production and what an installed-price scope should include; neither turns into a bill credit.
- Do not compare mismatched months.
- Distinguish a recorded credit from a payment, refund or elimination of charges.
- Record service, tariff or equipment changes during the period.
| Item | Useful question |
|---|---|
| Service period | What dates does this bill cover? |
| Consumption or imported energy | Which part records energy received from the grid? |
| Generation or exchange | Where is it shown and what unit is used? |
| Credit or adjustment | Which rule, period and tariff version does it cite? |
| Final balance | Which charges remain even where generation is recorded? |
Source: Resolution and Order for Motion to Submit Revised Tariff Book, NEPR-MI-2026-0005
Credits, charges and conditions to verify
LUMA describes an annual net-credit step in June for the preceding 12 months, while the act and tariff may contain eligibility and treatment conditions that need contextual reading. That supports asking questions; it does not support calculating an individual amount from a generic table or promising a zero balance.
Confirm the service, agreement and published tariff shown on the account, any pending interconnection documentation, and whether the meter and system are being read under the applicable process. A battery may support backup goals, but it does not automatically turn its capacity into a bill credit; read battery limits separately.
- Version and date of the tariff document consulted.
- Interconnection and tariff-change dates in the record.
- Period that LUMA attributes to a credit or adjustment.
- Charges not explained by generation that should be queried.
Source: Pasos de Medición Neta, Resolution and Order for Motion to Submit Revised Tariff Book, NEPR-MI-2026-0005, Puerto Rico Net Metering Program Act, Act No. 114 of August 16, 2007, as amended
Questions for LUMA and the installer
Ask LUMA about account status, agreement, published tariff and the meaning of bill entries. Ask the named installer about configuration, monitoring, commissioning date and documents it submitted; do not attribute an official bill interpretation to it without source support. Keep those answers in separate records.
If an explanation appears to rely on an older policy, request the current page or document and review date. This guide does not provide tariff advice or resolve billing disputes.
- What is my interconnection state in the portal?
- Which tariff and agreement are attached to my account?
- Which document explains this credit or charge?
- Which system configuration or measurement should the installer review?
Source: Pasos de Medición Neta, Resolution and Order for Motion to Submit Revised Tariff Book, NEPR-MI-2026-0005
Official sources and review date
Reviewed November 15, 2026: LUMA net-metering steps, Act 114-2007 as amended, and the Energy Bureau's 2026 tariff order. These sources establish that a process and rule-governed credits exist; they do not validate amounts, eligibility or results for an individual account.
This is a information page awaiting qualified review. Confirm the current agreement and tariff-book version before making a financial or contractual decision.
Source: Pasos de Medición Neta, Puerto Rico Net Metering Program Act, Act No. 114 of August 16, 2007, as amended, Resolution and Order for Motion to Submit Revised Tariff Book, NEPR-MI-2026-0005
Questions
Does net metering eliminate every charge?
It should not be assumed to. Review each entry and the current tariff applicable to the account; this guide does not promise a zero bill.
Source: Resolution and Order for Motion to Submit Revised Tariff Book, NEPR-MI-2026-0005
Does a battery automatically produce credits?
No. Storage function and billing treatment are separate matters that need confirmation for the system and account.
Source: Pasos de Medición Neta
Prepare a like-for-like comparison
Use a documented checklist to compare equipment, scope, warranties, payment terms and unresolved questions.
Compare solar quotesSources
- Pasos de Medición Neta — LUMA Energy, 2026-11-15
- Puerto Rico Net Metering Program Act, Act No. 114 of August 16, 2007, as amended — Puerto Rico Energy Bureau / Office of Management and Budget, 2026-11-15
- Resolution and Order for Motion to Submit Revised Tariff Book, NEPR-MI-2026-0005 — Puerto Rico Energy Bureau, 2026-11-15